Artemis

Draft

The United States programme to return crew to the lunar surface and establish sustained cislunar operations. The technical architecture is covered in Artemis and human lunar return; this page records the programme structure.

Announced
2019, building on earlier lunar programme direction
Lead
NASA, with international and commercial partners
Objective
Crewed lunar landing and sustained presence, with the south polar region as the target
Inherited elements
SLS and Orion trace to the Constellation programme cancelled in 2010

Elements and providers

ElementFunctionProvider
SLSHeavy lift to trans-lunar injectionNASA with Boeing, Northrop Grumman, Aerojet Rocketdyne
OrionCrew vehicle, deep space capableNASA with Lockheed Martin
European Service ModuleOrion propulsion, power, consumablesESA with Airbus
Gateway PPE and HALOPower and propulsion element, habitation moduleMaxar and Northrop Grumman
Human Landing SystemSurface accessSpaceX Starship HLS; Blue Origin Blue Moon
Surface mobilityRovers, pressurised and unpressurisedCommercial and international partners including JAXA
CLPS deliveriesRobotic payload delivery preceding crewMultiple commercial providers

The mixture of procurement models is characteristic. SLS and Orion are cost-plus developments with long heritage; HLS and CLPS are fixed-price service purchases. The programme therefore contains both models side by side, which makes it a useful comparison case for the argument in Space agencies.

Mission sequence

MissionProfileStatus
Artemis IUncrewed Orion to a distant retrograde lunar orbit and returnFlown November to December 2022, 25.5 days
Artemis IICrewed lunar flyby, no landingIn preparation
Artemis IIICrewed landing near the south poleDepends on HLS readiness
Artemis IV onwardGateway assembly, longer surface staysPlanned

Artemis I validated SLS, Orion, the trajectory and the heat shield at lunar return velocity of about 11 km/s, which is considerably more demanding than return from low Earth orbit. The heat shield exhibited more char loss than predicted, and characterising that behaviour became significant work before crewing the vehicle.

Partners

Artemis is explicitly a coalition programme rather than a national one.

PartnerContribution
ESAOrion service modules; Gateway modules
JAXAGateway contributions; pressurised lunar rover
CSACanadarm3 for Gateway
OthersVarious contributions and astronaut flight opportunities

The Artemis Accords are a separate instrument: bilateral agreements setting out principles for civil space activity including transparency, interoperability, emergency assistance, registration, scientific data release, heritage site preservation, deconfliction through safety zones, and debris mitigation.

Their significance is that they attempt to establish operating norms outside the United Nations treaty process, which has produced no new binding space treaty since 1979. The criticism is that a coalition led by one state, interpreting the Outer Space Treaty in ways favourable to resource extraction, is not equivalent to a multilateral agreement, and that safety zones sit uneasily with the non-appropriation principle. See Policy and regulation.

Programme risk

RiskCharacter
HLS readinessThe dominant schedule driver; depends on orbital cryogenic refuelling, never demonstrated at scale
Surface systemsNext-generation EVA suits are a long-lead item with their own development history
SLS cost and cadenceAn expendable vehicle at low flight rate; a cost question rather than a technical one
Political continuityThe programme spans multiple administrations; its predecessor was cancelled mid-development

The last row is not technical and is historically the most decisive. Constellation was cancelled in 2010 after five years and substantial expenditure, and the elements that survived did so by being repurposed into what became SLS and Orion. A programme whose critical path is a decade long is exposed to changes in priority that no engineering margin covers.

Programme against architecture

A distinction worth maintaining. Artemis is a programme: a set of funded elements, contracts, partners and missions. The architecture is the technical approach: SLS and Orion to a near-rectilinear halo orbit, transfer to a separately launched lander, descend, ascend, transfer back, return.

The architecture is partly a consequence of the programme rather than of engineering optimisation. Orion goes to NRHO rather than low lunar orbit because its service module lacks the delta-v for the latter, and it has that service module because of decisions made in a predecessor programme. A clean-sheet architecture would likely differ.

That is not a criticism so much as an observation about how large government programmes work: inherited elements constrain the architecture, and the architecture is then optimised within those constraints.

References

  • Smith, M. et al. “The Artemis Program: An Overview of NASA’s Activities to Return Humans to the Moon”, IEEE Aerospace Conference, 2020.
  • NASA Office of Inspector General audit reports on SLS, Orion, HLS and EVA suits.
  • The Artemis Accords, US Department of State, 2020 and subsequent signatures.
  • NASA Artemis mission documentation and Artemis I post-flight reports.